Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : CONSTRUCTION OF NEW INTERNATIONAL TERMINAL BUILDING(GOA).

Reported Date : 07-NOV-17

Monthly Report : 9 / 2017

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
335.610318

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
305.5900305.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20120/09/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks