Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : MODERNIZATION OF CHENNAI AIRPORT PHASE II, CHENNAI.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    52

Total/Pending/Completed Milestone - 13 / 1 / 12

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
246702467

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1580.736.0214.851601.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20226/20266/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2500

Ministry Review Date

LatestLastPhysical Progress (%)Status
71Ongoing

Monthly Status

Background Information

Expenditure in current month : 14.85 Cr. Over all (T 2 & T 3) -Physical progress : 71% Anticipated: T- 2 08.07.2023(T-2 commissioned ) T-3 works commenced on 23/05/2024 and foundation works is in progress. T-3 PDC 30/06/2026Anticipated: (Part-I & Part-II) (Part-II Shall be taken up after commissioning of Part-I) Part-1 31.03.2023 ( Part -1 works completed & commissioned ) Part-2 shall be started after demolition of old T3 terminal (Demolition of old T3 terminal completed upto ground level. Removal of foundation is in progress). Part-II PDC 31/12/2025

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone