Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
52
|
Total/Pending/Completed Milestone -
13
/
1
/
12
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Expenditure in current month : 14.85 Cr.
Over all (T 2 & T 3) -Physical progress : 71%
Anticipated: T- 2 08.07.2023(T-2 commissioned )
T-3 works commenced on 23/05/2024 and foundation works is in progress.
T-3 PDC 30/06/2026 | Anticipated:
(Part-I & Part-II)
(Part-II Shall be taken up after commissioning of Part-I)
Part-1 31.03.2023 ( Part -1 works completed & commissioned )
Part-2 shall be started after demolition of old T3 terminal (Demolition of old T3 terminal completed upto ground level. Removal of foundation is in progress).
Part-II PDC 31/12/2025 |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |