Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : CCS INTERNATIONAL AIRPORT , LUCKNOW.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   138.02

Time Overrun (Months)-    61

Total/Pending/Completed Milestone - 2 / 1 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
138319383291.81

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2622.429.413.72645.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/202110/202610/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1420

Ministry Review Date

LatestLastPhysical Progress (%)Status
80.37Ongoing

Monthly Status

Background Information

1. Physical progress as on 31-May-25 is 80.36% 2. Terminal 1 demolition work started in Aug-24, demolition work is Completed. 3. Available work front area provided to the contractor for foundation work. Construction work is in progress.1. Physical progress as on 31-Mar-24 is 63.2% 2. Financial progress as on 31-Mar-24 is 2089.61 Cr.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone