Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : CONSTRUCTION OF TERMINAL BUILDING AND ASSOCIATED WORKS AT LEH AIRPORT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   33.24

Time Overrun (Months)-    49

Total/Pending/Completed Milestone - 12 / 10 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
480.33640640

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
407.9301.15409.08

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/202110/202510/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
750

Ministry Review Date

LatestLastPhysical Progress (%)Status
63.67Ongoing

Monthly Status

Background Information

Manpower Mobilization under progress. SPCL has deployed 409 manpower as on date 31.05.2025 The manpower and lobour to be remobilize by the 2nd week of April 2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone