Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : AIRSIDE CAPACITY ENHANCEMENT OF NSBI AIRPORT, KOLKATA.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   1.87

Time Overrun (Months)-    18

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
389.71397397

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
396.6100396.61

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20215/20235/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.030

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

Work Completed.Work Completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone