Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : CONSTRUCTION OF NEW DORNESTIC TERMINAL BUILDING AND OTHER STRUCTURES, PHASE I AND II.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    32

Total/Pending/Completed Milestone - 3 / 2 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1216.901216.9

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
962.0825.2721.441008.79

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20226/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
97.070

Ministry Review Date

LatestLastPhysical Progress (%)Status
89.66Ongoing

Monthly Status

Background Information

Package -1 : Work Completed. The final Bill is under process. Package -2: NTB -Glazing, partition and final finishing work are in progress. Package -3: Work of VIP lounge, FCO Building & Hanger no 2 completed.Hangar -I and Hangar -III under Process.Package -1 : works in completion stage Package -2: Works in progress for RCC structures as well as fabrication of roof truss. Package -3: Work of VIP lounge final finishing in completion stage and FCO building completed , Hangar -I and Hangar -III under hindrance.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone