Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING AT LGBI AIRPORT GUWAHATI.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
114202333

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1750.24133.8964.321948.45

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20219/20259/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10970

Ministry Review Date

LatestLastPhysical Progress (%)Status
89.66Ongoing

Monthly Status

Background Information

June2025- Monthly Status achieve 2.37% = (43.22*100/1817.55)=2.37March 2024- Monthly Status achieved 2.18% = (32.77*100/1500)=2.18

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks