Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING AT LGBI AIRPORT GUWAHATI.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   104.29

Time Overrun (Months)-    53

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
114202333

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
993.93653.5102.811750.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20218/20258/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10970

Ministry Review Date

LatestLastPhysical Progress (%)Status
83.87Ongoing

Monthly Status

Background Information

March 2025- Monthly Status achieve 3.74% = (65.18*100/1740.94)=3.74March 2024- Monthly Status achieved 2.18% = (32.77*100/1500)=2.18

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone