Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : CONSTRUCTION OF DOMESTIC PASSENGER TERMINAL BUILDING AT DEHRADUN AIRPORT, DEHRADUN.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   9.44

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
456.86500500

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
483.860.1483.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20209/20249/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.10

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

The present status of Phase 01: Work completed and commissioned on 29.10.2021. Phase-2 (main work) completed on 17.01.2024, inaugurated on 14.02.2024 and commissioned on 15.02.2024. Supplementary work completed on 15.09.2024.The present status of Phase 01: Work completed and commissioned on 29.10.2021. The demolition of existing Terminal Building at site has been completed. Phase-2 (main work) provisionally completed on 17.01.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone