Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 9.44
|
Time Overrun (Months)-
48
|
Total/Pending/Completed Milestone -
7
/
0
/
7
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
The present status of Phase 01: Work completed and commissioned on 29.10.2021.
Phase-2 (main work) completed on 17.01.2024, inaugurated on 14.02.2024 and commissioned on 15.02.2024. Supplementary work completed on 15.09.2024. | The present status of Phase 01: Work completed and commissioned on 29.10.2021.
The demolition of existing Terminal Building at site has been completed.
Phase-2 (main work) provisionally completed on 17.01.2024.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |