Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : UPGRADATION OF JABALPUR AIRPORT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    37

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
412.240412.24

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
402.8100402.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20217/20247/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

Work Completed.1. Terminal Building works : Work Completed. 2. ATC Tower and ARP Building work : Glazing in ATC, False celling works, Toilet fittings work and other Finishing works in progress. PDC - 15.04.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone