The grading work is in finished in opearational area. The non operational wall is completed.
Full Runway completed, Apron and Isolation Bay completed. Finishing of Building works for Fire station, MT Pool and E & M workshop are completed. DVOR, Localizer Hut, GP Hut completed. Box culvert work completed. Regular Terminal Building & ATC Control Tower work completed. | The grading work is in finished in opearational area. The non operational wall is completed.
Full Runway completed, Apron and Isolation Bay completed. Finishing of Building works for Fire station, MT Pool and E & M workshop are completed. DVOR, Localizer Hut, GP Hut completed. Box culvert work completed. Terminal Building, ATC tower works are in progress. |