Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : DEVELOPMENT OF TUTICORIN AIRPORT.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   18.61

Time Overrun (Months)-    37

Total/Pending/Completed Milestone - 51 / 29 / 22

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
380.870451.74

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
251.0196.579.16356.74

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20224/20254/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
75120

Ministry Review Date

LatestLastPhysical Progress (%)Status
98.75Ongoing

Monthly Status

Background Information

Expenditure in current month: 9.16 Cr. Physical progress : 98.75 % Status: Runway work, Terminal Building, Fire Station works Completed. ATC Tower cum Technical Block work in progressExpenditure in current month : 20.16 Cr. Physical progress : As given above

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone