Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : C/O OF NITB AND ASSOCIATED WORK AT VIJAYAWADA AIRPORT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    29

Total/Pending/Completed Milestone - 14 / 8 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
611.80611.8

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
426.467.3910.9444.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20238/20258/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
74Ongoing

Monthly Status

Background Information

Expenditure in current month : 10.902 Cr. Physical progress : 74%Expenditure in current month :10crs Physical progress : 44.5%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone