Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : EXTENSION OF TERMINAL BUILDING, PTT, APRON AND CAR PARK AT SURAT AIRPORT..

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    49

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
353.250353.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
310.5835.531.52347.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20213/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2527.05

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

Work completed. Milestone Remarks: (1) Work Completed. (2) Extended Terminal Building is inaugurated by Hon’ble PM on 17/12/2023 and Extended Terminal Building is operationalized w.e.f. 25/12/2023. (3) Supplementary Agreement executed on 14/10/2023 for carrying out balance Work and Work is completed on 30/03/2024. (4) Final bill paid.Work in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks