Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 1.99
|
Time Overrun (Months)-
12
|
Total/Pending/Completed Milestone -
11
/
3
/
8
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Present Status of Project :
NTB : 100 %
Apron & Link Taxi : 100 %
B/wall: 100 %
Drain & Road: 100 %
PBB: 100 %
BHS: 100%
Anticipated: Put to operationation since 02.04.2024. Work completed on 08.08.2024
Status:Operation since 02.04.2024 | Present Status of Project :
NTB : 99.5 %
Apron & Link Taxi : 100 %
B/wall: 100 %
Drain & Road: 98 %
PBB: 100 %
BHS: 96%
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |