Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : DEVELOPMENT OF NEW GREENFIELD AIRPORT AT DHOLERA, AHMEDABAD (GUJARAT). PHASE-1..

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 15 / 12 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
13051143.951143.95

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
505.5498.9644.15648.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20250/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7850

Ministry Review Date

LatestLastPhysical Progress (%)Status
61Ongoing

Monthly Status

Background Information

SH: I Operational Area Work: X. Latest Status (Max 300 words) Part-I: Operational Area Works Status: - 1. 110.04 Lakhs Cum earth filling in Pavement area, Basic Strip/Non-Strip Area, Perimeter Road, Boundary wall, hard standing Area for embankment construction. 2. Runway - PQC 75423 cum completed out of 75600cum. 3. Runway Shoulder - PQC 13532 cum completed out of 13807 cum. 4. PTT - 07 Nos. Box Culvert completed for Aircraft portion in priority area for cargo operation. 5. Cargo Apron - PQC 12732 cum completed (Total 13000 cum). 6. Trapezoidal Drain - 6930 m completed out of 9770m. RCC U-Shape open Drain 2500 m length completed out of 2656m. RCC box drain PCC work 400 m length completed and raft 280 m Completed wall 270 m Completed and Slab 85 m out of 380m 7. Perimeter road - Earthwork 5.89 Lakhs Cum completed out of 5.93 Lakhs cum. 8. Operational Boundary Wall (Total 13.50 Km)- Foundation work 11.50 Km completed. Column & Panel erection 8.1 Km completed. Earthwork Level-II 8.0 Km completed. 9. Fire Station brick work Completed. Plaster & Floor Tiles work is in progress. AGL Substation inside & outside Plastering Work & POP work in progress. 10. OH, Tank RCC structure work completed. Waterproofing work Completed. 11. UG Tank Slab work completed. Waterproofing work pending. 12. DVOR Building Plaster Work is in progress. 13. Watch Tower work in progress (13 watch tower out of 15 watch tower) 14. GP & LLZ HUT external painting work completed. 15. Cooling Pit earth filling Completed. Fire Pit Structure completed. 16. Arbitration argument completed. Award issued on 23.04.2025. 17. Definitive Design of AGL and MEP System has been approved, Housing boxes, HDPE & GI Pipes for cable laying has been received at site. Cable laying work is in progress. AGL Housing box has been fixed on Runway shoulders. DG set has been installed in AGL substation.SH: I Operational Area Work: 95% Soil Stablization work under pavements is completed. Approx. 20.00 Lakhs Cum Earth filling in Runway, Apron, PTT, Strip and Non-Strip Area, Perimeter Road, Boundary wall, DVOR and Fire Station for embankment construction is compleated. Revised foundation design with open foundation for Ops wall submitted on 08.01.2024 is vetted from NIT Surat. Precast RCC panels / Columns casting for boundary wall is in progress. Erection of Ops Boundary wall is in progress. Other structure like Fire station, DVOR, GP, Cooling pit, Fire pit, UG tank, OH Tank etc. has been vetted from NIT, Surat. Testing of test pile for fire station, DVOR, AGL substation and OH tank completed. Quarry permit for 22.23 Lakhs Cum has been issued by Geo & Mines deptt. for identified borrow areas Survey no. 318, 1362, 34, 26, 1363, 16, 371. SH: II Non Operational Area Works: Name of Work:“Construction of New Integrated Passenger Terminal Building, ATC Tower Cum Technical Block, Cargo Complex, ESS Building, Car Parking, Approach Roads, Ancillary Structures, Allied Works and Associated Electrical Works”. L1 bidder: M/s Yashnand Engineers & Contractor Pvt. Ltd, Ahmedabad Quoted amount Rs. 333.00 Cr. which is 5.30% of estimated cost. Award of Work: 01.01.2024. Stipulated date of start: 11.01.2024 Stipulated date of completion: 10.07.2025 Current status: : Agency has submitted Performance BG of Rs. 16.65 Cr. Soil investigation work completed and test reports received. Pile load test completed and test report received. Structural design of pile foundation for Cargo bldg & ATC cum Technical block received & for PTB is in progress. Concrete batch mix plant installation i/c calibration completed. Pile foundation in Cargo building area started from 28.03.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks