Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : DEVELOPMENT OF NEW GREENFIELD AIRPORT AT DHOLERA, AHMEDABAD (GUJARAT). PHASE-1..

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 15 / 12 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
13051143.951143.95

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
80.26361.6863.6505.54

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20250/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
188.950

Ministry Review Date

LatestLastPhysical Progress (%)Status
50Ongoing

Monthly Status

Background Information

SH: I Operational Area Work: X. Latest Status (Max 300 words) Part-I: Operational Area Works Status: - 1. 100% Soil Stabilization work under pavements is completed. Approx. 96 Lakhs Cum earth filling in Pavement area, Basic Strip/Non-Strip Area, Perimeter Road, Boundary wall, hardstanding Area for embankment construction. 2. Runway - PQC 70600 cum completed out of 76000cum. 3. Runway Shoulder - PQC 8302 cum completed out of 14640 cum. 4. Runway - Utility pipe laying for cable crossing completed at 4 locations in Runway, PTT and Cargo Taxi. 5. PTT - DRLC 3100m in length completed. PQC 3100m in length completed. 6. PTT - Utility pipe laying for cable crossing completed at 4 locations in PTT. 7. PTT - 07 Nos. Box Culvert completed for Aircraft portion in priority area for cargo operation. 8. Cargo Apron - PQC 2115 cum completed. Cargo Taxi 550 Cum completed (Total 8000 cum). Extended portion of Cargo Apron - earth filling in progress. 9. Trapezoidal Drain - 5620 m completed out of 9770m. RCC U-Shape open Drain 2335 m length completed out of 2656m . RCC box drain PCC work 400 m length completed and raft 280 m Completed and wall 270 m Completed out of 505m 10. Perimeter road - Earthwork 4.35 Lakhs Cum completed out of 5.93 Lakhs cum. 11. Operational Boundary Wall - Foundation work 8.27 Km completed (Total 13.50 Km). Column & Panel erection 4.20 Km completed (Total 13.50 Km). Earthwork Level-II 2.0 Km completed (Total 13.50 Km) 12. Fire Station brick work Completed. Plaster & Floor Tiles work is in progress. AGL Substation cable trench work & brick work is in progress. 13. OH Tank RCC structure work completed. Waterproofing work is in progress. 14. DVOR Building column work completed. 15. Watch Tower work in progress (11 watch tower out of 15 watch tower 16. GP foundation work completed. LLZ HUT and GP HUT Foundation Raft Completed with toilet Block 17. Cooling Pit earth filling Completed. Fire Pit Structure completed.SH: I Operational Area Work: 95% Soil Stablization work under pavements is completed. Approx. 20.00 Lakhs Cum Earth filling in Runway, Apron, PTT, Strip and Non-Strip Area, Perimeter Road, Boundary wall, DVOR and Fire Station for embankment construction is compleated. Revised foundation design with open foundation for Ops wall submitted on 08.01.2024 is vetted from NIT Surat. Precast RCC panels / Columns casting for boundary wall is in progress. Erection of Ops Boundary wall is in progress. Other structure like Fire station, DVOR, GP, Cooling pit, Fire pit, UG tank, OH Tank etc. has been vetted from NIT, Surat. Testing of test pile for fire station, DVOR, AGL substation and OH tank completed. Quarry permit for 22.23 Lakhs Cum has been issued by Geo & Mines deptt. for identified borrow areas Survey no. 318, 1362, 34, 26, 1363, 16, 371. SH: II Non Operational Area Works: Name of Work:“Construction of New Integrated Passenger Terminal Building, ATC Tower Cum Technical Block, Cargo Complex, ESS Building, Car Parking, Approach Roads, Ancillary Structures, Allied Works and Associated Electrical Works”. L1 bidder: M/s Yashnand Engineers & Contractor Pvt. Ltd, Ahmedabad Quoted amount Rs. 333.00 Cr. which is 5.30% of estimated cost. Award of Work: 01.01.2024. Stipulated date of start: 11.01.2024 Stipulated date of completion: 10.07.2025 Current status: : Agency has submitted Performance BG of Rs. 16.65 Cr. Soil investigation work completed and test reports received. Pile load test completed and test report received. Structural design of pile foundation for Cargo bldg & ATC cum Technical block received & for PTB is in progress. Concrete batch mix plant installation i/c calibration completed. Pile foundation in Cargo building area started from 28.03.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone