Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : CONSTRUCTION OF NEW TERMINAL BUILDING AT JODHPUR AIRPORT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    11

Total/Pending/Completed Milestone - 3 / 3 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4800480

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
217.2029.47246.67

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/202410/202510/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1100

Ministry Review Date

LatestLastPhysical Progress (%)Status
70Ongoing

Monthly Status

Background Information

Work awarded on 10.05.2023. New Passenger Terminal Building work is in progress. New Passenger Terminal Building : Erection of purlin works are in progress. Roofing & GRC work in-progress. Granite & tile flooring, facade & false ceiling work is in-progress. A/D Toilets & AHU area tile & finishing works are in progress. MEP services works like fire fighting, HVAC ducting etc. works in progress. Utility building : Finishing works is in-progress. STP & WTP MEP services works in progress HVAC chillers, escalators, DG sets, transformers installed at site & Car parking in phase manner & city side External & land development works is in progress. Work awarded on 10.05.2023. Site enabeling work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone