Work awarded on 10.05.2023. New Passenger Terminal Building work is in progress.
New Passenger Terminal Building :
Erection of purlin works are in progress. Roofing & GRC work in-progress. Granite & tile flooring, facade & false ceiling work is in-progress. A/D Toilets & AHU area tile & finishing works are in progress. MEP services works like fire fighting, HVAC ducting etc. works in progress. Utility building : Finishing works is in-progress. STP & WTP MEP services works in progress HVAC chillers, escalators, DG sets, transformers installed at site & Car parking in phase manner & city side External & land development works is in progress. | Work awarded on 10.05.2023. Site enabeling work is in progress. |