Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : UDAIPUR AIRPORT- CONSTRUCTION OF NEW INTEGRATED PASSENGER TERMINAL BUILDING.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 2 / 2 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
8870887

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
285.9714.540300.51

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20260/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
92.510

Ministry Review Date

LatestLastPhysical Progress (%)Status
62Ongoing

Monthly Status

Background Information

Floorng, Façade, Roof sheeting, WTP, STP, road work & MEP works are in progress.Contractor has taken over site on 11.11.2023 and mobilisation is completed. Work In Progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone