Forecourt area RCC slab under progress WTP, STP and elevated road works. Roof sheeting, granite flooring & MEP works is in progress
Milestone status: RCC work of Terminal Building is completed. Forecourt area RCC slab is in progress. RCC slab work for elevated road in progress. Utility block & Service Tunnel RCC work completed and WTP & STP works are in progress. Fabrication/ Erection work for structural steel of roof truss, Facade & Deck slab are in progress. Roof sheeting & Granite flooring work are in Progress. Road work is in progress. MEP like fire fighting, HVAC Ducting work are in progress.
Remarks: The completion date has been revised on account of PEOT approved by ED Engg.- NR for the hindrances up to 07.09.2024 and additional scope of work approved by planning directorate. | Contractor has taken over site on 11.11.2023 and mobilisation is completed. Work In Progress. |