Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
3
/
3
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Approval of Drawing Under Process.
Milestone 1 Status: Work is in progress
Terminal Building Work was awarded on 12/12/2023.
Excavation, PCC and RCC of footing of Terminal Building and Elevated road are completed.
Waterproofing, PCC work and RCC work for grade slab completed.
RCC work of column and slab in Elevated Road is in progress.
The scaffolding, reinforcement and shuttering work for beam and slab , Structural steel composite work are in progress.
Road work, strom water drainage work are also in progress. | Work in progress |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |