Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : JAMMU - CONSTRUCTION OF NEW CIVIL ENCLAVE.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 3 / 3 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
861.370861.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
132.411.4110.83144.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20260/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
900

Ministry Review Date

LatestLastPhysical Progress (%)Status
30Ongoing

Monthly Status

Background Information

Approval of Drawing Under Process. Milestone 1 Status: Work is in progress Terminal Building Work was awarded on 12/12/2023. Excavation, PCC and RCC of footing of Terminal Building and Elevated road are completed. Waterproofing, PCC work and RCC work for grade slab completed. RCC work of column and slab in Elevated Road is in progress. The scaffolding, reinforcement and shuttering work for beam and slab , Structural steel composite work are in progress. Road work, strom water drainage work are also in progress. Work in progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone