Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : HUBBALI AIRPORT - CONSTRUCTION OF NEW DOMESTIC TERMINAL BUILDING AND MISCELLANEOUS WORKS.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 29 / 29 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
320.470320.47

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
49.670.8450.51

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20260/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
600

Ministry Review Date

LatestLastPhysical Progress (%)Status
27.5Ongoing

Monthly Status

Background Information

Expenditure in current month : 0.84 Physical progress : 27.50%Work awarded on 12.01.2024. Site has been handed over to agency on 18.01.2024. Mobilization is in progress. GFC Drawings is yet to be submitted by agency. Foundation Excavation, PCC and Reinforcement work in progress Expenditure in current month : 1.73 Cr Physical progress : 1.00%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone