Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NORTHERN COAL FIELDS LIMITED.
Project Name : KRISHNASHILA (NCL) (4MTY).

Reported Date : 07-JUN-16

Monthly Report : 4 / 2016

  

   

Total/Pending/Completed Milestone - 5 / 3 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
789.88741.62741.62

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
464.9446.250511.19

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20130/03/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
78.1285.27

Ministry Review Date

LatestLastPhysical Progress (%)Status
28-JAN-1621-NOV-060Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks