Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NORTHERN COAL FIELDS LIMITED.
Project Name : BLOCK-B OCP NCL (3.5 MTY).

Reported Date : 14-MAR-16

Monthly Report : 1 / 2016

  

   

Total/Pending/Completed Milestone - 6 / 3 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
746.04535.1535.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
348.3375.85126.14550.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20150/03/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
94.8798.61

Ministry Review Date

LatestLastPhysical Progress (%)Status
01-JUL-1521-NOV-060Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks