Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NORTHERN COAL FIELDS LIMITED.
Project Name : NIGAHI OC EXPANSION PROJECT 10 MTY TO 15 MTY, SINGRAULI.

Reported Date : 16-MAY-19

Monthly Report : 4 / 2019

  

   

Total/Pending/Completed Milestone - 3 / 2 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
259.40486.57

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
266.3800266.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20120/04/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks