Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 6.18
|
Time Overrun (Months)-
120
|
Total/Pending/Completed Milestone -
12
/
11
/
1
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Notification of 42 Ha additional land u/s 11 (i) of CBA, (A&D) Act
Status-Additional 42Ha land notified U/s 9(i) of CBA (A&D) Act on 15.04.25. Proposal for notification U/s 11(i) is under preparation | Proposal for notification of additional Land U/s 4(i) granted by Moc on 03.07.23. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |