Project Summary
Project Summary
Sector Name : COAL.
Agency Name : EASTERN COAL FIELDS LIMITED.
Project Name : RAJMAHAL OC EXP..

Reported Date : 22-JAN-19

Monthly Report : 12 / 2018

  

   

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
153.820153.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
131.0700131.07

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20140/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks