Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : PENGANGA OCP(REVISED).

Reported Date : 03-DEC-20

Monthly Report : 10 / 2020

  

   

Total/Pending/Completed Milestone - 11 / 3 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
441.820441.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
257.672.150259.82

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
30.280

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks