Project Summary
Project Summary
Sector Name : COAL.
Agency Name : CENTRAL COAL FIELDS LIMITED.
Project Name : CHURI BENTI UG (0.81 MTY).

Reported Date : 05-NOV-24

Monthly Report : 10 / 2024

  

   

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
163.510163.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
133.28.070133.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20110/010/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
9.160

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-MAY-2484.4Completed

Monthly Status

Background Information

Coal Production in Oct 24 Coal Target:0.05 MT, Actual:0.05 MT Coal Production in Mar 24 Coal Target:0.09 MT, Actual:0.05 MT

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks