Project Summary
Project Summary
Sector Name : COAL.
Agency Name : CENTRAL COAL FIELDS LIMITED.
Project Name : PURNADIH OCP (3.0 MTY).

Reported Date : 08-FEB-18

Monthly Report : 12 / 2017

  

   

Total/Pending/Completed Milestone - 4 / 1 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
210.980210.98

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
203.922.880206.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20130/012/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
20.270

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-SEP-17100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks