Project Summary
Project Summary
Sector Name : COAL.
Agency Name : CENTRAL COAL FIELDS LIMITED.
Project Name : TAPIN OCP (2.5 MTY).

Reported Date : 16-JUN-20

Monthly Report : 3 / 2020

  

   

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
264.680264.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
179.871.30181.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20120/03/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3.470

Ministry Review Date

LatestLastPhysical Progress (%)Status
85.6Completed

Monthly Status

Background Information

Coal Production and OBR in MAR’20 Coal Target:0.104 MT, Actual:0.0742MT OBR Target:0.332 MCUM, Actual:0.167MCUM

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks