Project Summary
Project Summary
Sector Name : COAL.
Agency Name : CENTRAL COAL FIELDS LIMITED.
Project Name : KARMA OCP (1.0MTY).

Reported Date : 13-AUG-24

Monthly Report : 8 / 2024

  

   

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
162.460162.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
95.75.17095.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20140/09/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1.170

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-MAY-23100Completed

Monthly Status

Background Information

Coal Production and OBR in Mar 24 Coal Target:0.13 MT, Actual:0.14 MT OBR Target:0.20 MCUM, Actual:0.08 MCUM

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks