Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : NEYVELI NEW THERMAL POWER PROJECT(2X500 MW).

Reported Date : 08-FEB-24

Monthly Report : 1 / 2024

  

   

Total/Pending/Completed Milestone - 35 / 0 / 35

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5907.1189908990

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
7590.49327.9650.467968.91

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20152/20212/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4000

Ministry Review Date

LatestLastPhysical Progress (%)Status
16-MAR-2299.8Completed

Monthly Status

Background Information

Unit-I commercial operation started from 28.12.2019 and Unit-II commercial operation started from 10.02.2021. Project completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks