Project Summary
Project Summary
Sector Name : COAL.
Agency Name : BHARAT COKING COAL LIMITED.
Project Name : MOONIDIH XV SEAM UG.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    86

Total/Pending/Completed Milestone - 6 / 3 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1230.2701230.27

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
602.161.662.17605.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/05/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
300

Ministry Review Date

LatestLastPhysical Progress (%)Status
81Ongoing

Monthly Status

Background Information

1. Due to force majeure situation arising out of war with Russia a lot of infrastructure of M/S CORUM has got destroyed in Ukraine for which supply of longwall equipment is being delayed. 2. In-seam development is going on for preparation of Gate Roads. Progress of in-seam drivage was very slow due to frequent encounter of geological disturbances. 3. BCCL is taking all possible steps to expedite the operation of the Project.1. Due to force majeure situation arising out of war with Russia a lot of infrastructure of M/S CORUM has got destroyed in Ukraine for which supply of longwall equipment is being delayed. Supply of longwall equipment expected by Jan 2025. 2.In-seam development was going on for preparation of Trunk Roads and progress of in-seam drivage was very slow due to frequent encounter of geological disturbances.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone