Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : WIND POWER PROJECT,KAZHUNEERKULAM,TAMILNADU.

Reported Date : 07-DEC-17

Monthly Report : 10 / 2017

  

   

Total/Pending/Completed Milestone - 10 / 0 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
364.750364.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
333.0500333.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20146/201710/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
98Completed

Monthly Status

Background Information

Project completed on 18.07.2017.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks