Project Summary
Project Summary
Sector Name : COAL.
Agency Name : MAHANADI COAL FIELDS LIMITED.
Project Name : BASUNDHARA (WEST) OC EXTN(7.00 MTY).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 9 / 5 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
479.150479.15

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
267.05.154.79271.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/03/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
134.810

Ministry Review Date

LatestLastPhysical Progress (%)Status
13-JUN-2563.04Ongoing

Monthly Status

Background Information

The Project Basundhara west extension OCP was approved in May-2014

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks