Project Summary
Project Summary
Sector Name : COAL.
Agency Name : MAHANADI COAL FIELDS LIMITED.
Project Name : JAGANNATH RE-ORGANISATION OC.(6.00 MTY).

Reported Date : 11-JAN-21

Monthly Report : 12 / 2020

  

   

Total/Pending/Completed Milestone - 7 / 2 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
337.660337.66

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
224.9833.670258.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/03/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
17.610

Ministry Review Date

LatestLastPhysical Progress (%)Status
09-SEP-200Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks