Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : MAKARDHOKRA I OC.

Reported Date : 17-JUL-19

Monthly Report : 5 / 2019

  

   

Total/Pending/Completed Milestone - 12 / 0 / 12

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
266.230266.23

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
144.3800144.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/05/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3.040

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Completed project. 292nd WCL Board held on 09.09.2017 approved the Completion Report of the Project with a Completion cost of Rs. 233.76 cr. with a provision for balance activities wef March-2017.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks