Project Summary
Project Summary
Sector Name : COAL.
Agency Name : BHARAT COKING COAL LIMITED.
Project Name : MADHUBAND NLW WASHERY.

Reported Date : 18-FEB-25

Monthly Report : 2 / 2025

  

   

Total/Pending/Completed Milestone - 8 / 4 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
289.450302

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
299.38.630300.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20140/011/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
103

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

1. PG Test Completed 2. Commercial operation has been started from 29.11.2023. 3. Pending job of 5.0 Mtpa Madhuband coal washery is being taken up by both BCCL and BOM operator and likely to be completed by May 2024. 4. Tender for completion of balance civil work of 5.0 Mtpa Madhuban Coal Washery has been floated on 12.03.2024 at the risk & cost of M/s HEC.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks