Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : SINGHORI OC MINE.

Reported Date : 27-OCT-21

Monthly Report : 10 / 2021

  

   

Total/Pending/Completed Milestone - 10 / 1 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
205.490205.49

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
138.12.460138.58

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20209/202110/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
15.740

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks