Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SOUTH-EASTERN COAL FIELDS LIMITED.
Project Name : AMGAON OPENCAST PROJECT RCE.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    60

Total/Pending/Completed Milestone - 6 / 3 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
316.10316.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
156.193.0427.78187.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
17.790

Ministry Review Date

LatestLastPhysical Progress (%)Status
49.4Ongoing

Monthly Status

Background Information

Disbursement of additional 10 % compensation amount of land & asset of Patna Village. Out of Rs 127.59 Crores approved compensation for Land & Asset, Rs 96.97 Crore has been disbursed.Disbursement of additional 10 % compensation amount of land & asset of Patna Village. Out of Rs 127.59 Crores approved compensation for Land & Asset, Rs 96.97 Crore has been disbursed

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone