Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SOUTH-EASTERN COAL FIELDS LIMITED.
Project Name : AMGAON OPENCAST PROJECT RCE.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    72

Total/Pending/Completed Milestone - 6 / 3 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
316.10316.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
187.131.20188.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20203/20263/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10.240

Ministry Review Date

LatestLastPhysical Progress (%)Status
65Ongoing

Monthly Status

Background Information

Approval of estimate of road for diversion of PMGSY road of Patna Village. Status- Achieved. Approved by CoFD on 30.12.2024Disbursement of additional 10 % compensation amount of land & asset of Patna Village. Out of Rs 127.59 Crores approved compensation for Land & Asset, Rs 96.97 Crore has been disbursed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone