Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SOUTH-EASTERN COAL FIELDS LIMITED.
Project Name : AMGAON OPENCAST PROJECT RCE.

Reported Date : 09-SEP-21

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 10 / 2021

Cost Overrun (%)-   0

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 6 / 3 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
316.10316.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
142.33.970146.27

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
13.810

Ministry Review Date

LatestLastPhysical Progress (%)Status
03-JAN-2078Ongoing

Monthly Status

Background Information

Stage -II FC obtained on 07.08.2020 . APCCF(LM), Raipur forwarded the compliance to CG State on 27.08.2021 for handover permission. CG State given approval for handover vide letter dated 27.09.2021Stage-I FC for 93.58 Ha forest land issued by MOEF on 15.04.2019.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone