Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SOUTH-EASTERN COAL FIELDS LIMITED.
Project Name : AMADAND OPENCAST EXPANSION PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    72

Total/Pending/Completed Milestone - 6 / 1 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
869.440869.44

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
271.16.58.35272.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20213/20273/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
33.240

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-DEC-2475Ongoing

Monthly Status

Background Information

Floating of NIT for Silo/CHP for Amadand OCP. Status-NIT for Silo/CHP is under preparation at CMPDI, RI-V.Work awarded for diversion of road on 18.10.2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone