Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : AMALGAMATED GONDEGAON GHATROHAN OC.

Reported Date : 27-OCT-21

Monthly Report : 10 / 2021

  

   

Total/Pending/Completed Milestone - 9 / 3 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
198.68325.18325.18

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
253.1719.730272.9

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/010/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
28.980

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks