Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : NEYVELI SOLAR POWER PROJECT 130 MW.

Reported Date : 06-DEC-18

Monthly Report : 10 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
687.28759.19759.19

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
758.300758.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/201712/201710/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
13-JUN-18100Completed

Monthly Status

Background Information

The project was commissioned in December-2017. The balance activities are completed in September-2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks