Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : NEYVELI UTTAR PRADESH POWER PROJECT LIMITED 1980 MW.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   26.36

Time Overrun (Months)-    47

Total/Pending/Completed Milestone - 48 / 15 / 33

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1723721780.9421780.94

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
17142.312289.25236.2119667.77

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20216/202510/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
14902000

Ministry Review Date

LatestLastPhysical Progress (%)Status
20-MAR-2589.6Ongoing

Monthly Status

Background Information

*Unit-1 (660 MW) has successfully started commercial operations from 00:00 hours on 12.12.2024. *Physical Progress of GA1: 96.82%, GA2: 97.76%, GA3:83.30% & GA4: 54.82%. GA4-Flue Gas Desulphurization: *Compressor Building: Foundation works under progress. *Tanks: 9/10 Nos: Foundation works completed. Fabrication under progress. *Damper Erection at Chimney Duct – Unit-2 – Completed.1)GA3 Package Contractor, BGRESL has filled with BSE on 05.04.2024 that NCLT passed CIRP by appointing IRP vide dated 03.04.2024. 2)GA4 FGD package : L2 Schedule approval under progress, Absorber-2,Limestone cum gypsum storage building,Unit-1 Duct Civil works are in progress. 3) Bridge Coal Linkage for coal supply:SLC(LT) no. 03/2024 vide its minutes dtd 07.03.2024 has recommended 4.26 MT coal from CIL mines for 1 year period (FY24-25). 4)During the meeting held on 21.12.2023, CMD/NCL has agreed in-principle to meet entire commissioning coal requirement of GTPP.NLCIL requested CIL the same in letter dated 26.12.2023. First rake of coal reached GTPP on 12th March 2024. 16 Nos. of rack unloaded at GTPP site as on 31.03.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone