*Unit-2 stage-II Steam blowing is under progress.
*FGD Works under progress.
*NLCIL signed MoU with ECL for diversion of 2 MT bridge linkage coal from ECL (G7 to G11 grade) on 29.04.2025. 2.2 Lakh ton coal received at site out of signed MoU quantity of 20 lakh ton.
*Further, CIL vide letter dated 29.05.2025, allocated 4.686 MT coal from ECL (Grade-G7 to G13), 0.586 MT coal from NCL (Grade-G7 to G13), 0.565 MT coal from CCL (Grade-G5 to G14, Washery IV-V).
*3.95 lakh ton commissioning coal from NCL Mines for Unit-1, Unit-2 and Unit-3 unloaded at GTPP site. | 1)GA3 Package Contractor, BGRESL has filled with BSE on 05.04.2024 that NCLT passed CIRP by appointing IRP vide dated 03.04.2024.
2)GA4 FGD package : L2 Schedule approval under progress, Absorber-2,Limestone cum gypsum storage building,Unit-1 Duct Civil works are in progress.
3) Bridge Coal Linkage for coal supply:SLC(LT) no. 03/2024 vide its minutes dtd 07.03.2024 has recommended 4.26 MT coal from CIL mines for 1 year period (FY24-25).
4)During the meeting held on 21.12.2023, CMD/NCL has agreed in-principle to meet entire commissioning coal requirement of GTPP.NLCIL requested CIL the same in letter dated 26.12.2023. First rake of coal reached GTPP on 12th March 2024. 16 Nos. of rack unloaded at GTPP site as on 31.03.2024.
|