Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : DURGAPUR EXTENSION (DEEP) OC (3.0 MTY).

Reported Date : 30-DEC-24

Monthly Report : 12 / 2024

  

   

Total/Pending/Completed Milestone - 6 / 1 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3280328

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
321.05.3857.44378.87

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20213/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
17.40

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Mine is under operation. Out of 410.96 Ha, 289.38 Ha land is in physical possession. Forestry clereance for stage II for 121.58 Ha land issued on 22.12.2021. Possession not yet received. Wildlife Clearance issued on 19.05.2023.Possession not yet received. EC exists for 3.0 MTY. During 2022-23, production is 1.7252 MT. Reason of delay: Project could not achieve its PR capacity due to delay in diversion of 121.58 Ha forest land. Stage II issued on 22.12.2021.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks