Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SINGARENI COLLIERS COMPANY LIMITTED.
Project Name : KAKATIYAKHANI OPENCAST III PROJECT PHASE-1.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 11 / 3 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
413.840413.84

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
397.5400397.54

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
19.820

Ministry Review Date

LatestLastPhysical Progress (%)Status
85Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks