Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SINGARENI COLLIERS COMPANY LIMITTED.
Project Name : SRP OC-II EXPANSION PROJECT.

Reported Date : 02-JUL-24

Monthly Report : 6 / 2024

  

   

Total/Pending/Completed Milestone - 6 / 2 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
272.730272.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
204.4465.210269.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20180/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5.330

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project Completion Report is under preparation

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks