Out of 1285.12 Ha land of PR provision, 1256.32 Ha land is in physical possession. Balance is in progress. EC existing for 3.50 MTY. During 2022-23, production is 1.7559 MT. Reason of delay: Project has to produce 1.60 MT coal in 2020-21 for completion but achieved 1.538 MT in 2020-21. The reasons of less production are explosive crises and impact of lockdown due to pandemic. Rehabilitation of Pimpalgaon village is involved which may take time.
| Out of 1285.12 Ha land of PR provision, 1256.32 Ha land is in physical possession. Balance is in progress. EC existing for 3.50 MTY. During 2022-23, production is 1.7559 MT. Reason of delay: Project has to produce 1.60 MT coal in 2020-21 for completion but achieved 1.538 MT in 2020-21. The reasons of less production are explosive crises and impact of lockdown due to pandemic. Rehabilitation of Pimpalgaon village is involved which may take time.
|