Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 34.2
|
Time Overrun (Months)-
48
|
Total/Pending/Completed Milestone -
4
/
2
/
2
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Out of 1285.12 Ha land of PR provision, 1256.32 Ha land is in physical possession. Balance is in progress. EC existing for 3.50 MTY. During 2022-23, production is 1.7559 MT. Reason of delay: Project has to produce 1.60 MT coal in 2020-21 for completion but achieved 1.538 MT in 2020-21. The reasons of less production are explosive crises and impact of lockdown due to pandemic. Rehabilitation of Pimpalgaon village is involved which may take time. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |