Project Summary
Project Summary
Sector Name : COAL.
Agency Name : WESTERN COAL FIELDS LIMITED.
Project Name : UKNI DEEP OC.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 4 / 3 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
318.140318.14

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
247.484.76.46252.7

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20213/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
9.490

Ministry Review Date

LatestLastPhysical Progress (%)Status
86Ongoing

Monthly Status

Background Information

Out of 1285.12 Ha land of PR provision, 1256.32 Ha land is in physical possession. Balance is in progress. EC existing for 3.50 MTY. During 2022-23, production is 1.7559 MT. Reason of delay: Project has to produce 1.60 MT coal in 2020-21 for completion but achieved 1.538 MT in 2020-21. The reasons of less production are explosive crises and impact of lockdown due to pandemic. Rehabilitation of Pimpalgaon village is involved which may take time. Out of 1285.12 Ha land of PR provision, 1256.32 Ha land is in physical possession. Balance is in progress. EC existing for 3.50 MTY. During 2022-23, production is 1.7559 MT. Reason of delay: Project has to produce 1.60 MT coal in 2020-21 for completion but achieved 1.538 MT in 2020-21. The reasons of less production are explosive crises and impact of lockdown due to pandemic. Rehabilitation of Pimpalgaon village is involved which may take time.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone