Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : TALABIRA II AND III OCP.

Reported Date : 04-JUN-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 22 / 3 / 19

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2401.0702401.07

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1581.4245.2901626.71

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20270/01/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4000

Ministry Review Date

LatestLastPhysical Progress (%)Status
04-APR-2586Completed

Monthly Status

Background Information

* Plant, commercial operation declared and 12.641 MT production achieved in FY2023-24. * CHP, Railway siding works are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks