Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : TALABIRA II AND III OCP.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 22 / 3 / 19

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2401.0702401.07

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1177.14317.7786.511581.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20270/01/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100200

Ministry Review Date

LatestLastPhysical Progress (%)Status
05-DEC-2460.1Ongoing

Monthly Status

Background Information

"* OB removal and dumping, coal excavation and stocking & Coal dispatch being carried out. * Commercial operation declared on 01.04.2021. * Production of coal for FY 2024-25 is 17.20 MT. *Talabira II & III OCP- CHP & SILO are under MDO Scope (8 MTPA) *Budgeted Expenditure-522.45 Cr, Actual Expenditure-231 Cr. *Scheduled DOC:Dec-2024 & Anticipated DOC: June-2025. ** Plant, commercial operation declared and 12.641 MT production achieved in FY2023-24. * CHP, Railway siding works are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone