Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NORTHERN COAL FIELDS LIMITED.
Project Name : BINA KAKRI AMALGAMATION OCP 14 MTPA.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 6 / 2 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
836.420836.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
726.6142.03.63769.27

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
240.260

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-SEP-2385.95Ongoing

Monthly Status

Background Information

1.Environmental Clearance:ToR for 17.50 MTPA accorded on 23.12.2024. Draft EIA EMP is under preparation at CMPDIL. 2.MP Forest land (353.76 Ha):Stage II issued on 16.04.2024. 3.UP Forest Land (30.50 Ha):EDS raised by DFO renukoot on 24.05.2025 4.Overall physical progress of 9.5 MTPA CHP:96%1.Environmental Clearance:MoEFCC accorded validity extension and amendment of EC on 06.03.2024. 2.MP Forest land (353.76 Ha, Revised: 288.844 Ha): After RO inspection, NO, Bhopal forwarded the proposal in the Parivesh portal to MoEFCC on 24.01.2024. MoEFCC vide letter dated 15.03.2024 communicated the decision of FAC to Govt. of MP for removing the condition in Stage I FC regarding excluding VDF patches for mining. Govt. of MP has recommended to MoEFCC for issuance of Stage II FC vide letter dated 21.03.2024. Issuance of Stage II FC letter is awaited. 3.UP Forest Land (30.50 Ha): The search for nonforest land for compensatory afforestation was pursued with RO, MoEFCC, Lucknow, following updated guidelines. The project submitted an undertaking to DFO Renukoot on 12.09.2023, with additional queries raised by DFO Renukoot on 21.09.2023. Furthermore, the Revenue department of the Government of Uttar Pradesh was asked to confirm the availability of NonForest Land for CA Purpose on 21.11.2023. D(T/PP), NCL, in a letter dated 21.11.2023 to the Additional Chief Secretary of the Revenue department, requested confirmation of the availability of nonforest land for CA Purpose. GM(Bina) also requested DM, Sonbhadra, to provide 30.5 Ha of nonforest land for CA purpose via a letter dated 20.01.2024. 4.Overall physical progress of 9.5 MTPA CHP:78%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone