Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : PACHWARA SOUTH COAL BLOCK.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 11 / 4 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2242.922242.92242.9

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
540.843.01103.65687.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20280/09/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5000

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-JUN-2554Ongoing

Monthly Status

Background Information

*Consent to Establish (CTE) issued by Jharkhand State Pollution Control Board, Ranchi on 16.04.2025. *Letter has been submitted to DFO, Dumka on 06.05.2025 for constitution and finalization of team by PCCF Ranchi, comprising officials from User agency and Forest department for study and monitoring the soil erosion, water conservation, ecological restoration activities in and around the project area. *Payment of Rs. 7,38,57,000.00/- has been made to DFO, Dumka regarding De-siltation of Ponds under FC- Studies on 16.05.2025. *Revised Demand note for payment of Rs.8.98 Crores towards the implementation of plantation activity within safety zone of PSOCP has been received from DFO, Dumka on 17.05.2025. Payment was made in CAMPA fund on 21.05.2025. *EDS compliance submitted to DFO, Dumka on 22.05.2025. Currently proposal is with RCCF. Forest Clearance: * Reply of EDS compliance has been uploaded on 19.03.2024. Currently proposal is with PCCF (Nodal Officer), Ranchi. * CMD/NLCIL vide letter dated 23rd March 2024 requested DG Forest and Spl Secretary, MoEF and CC for expediting the Forest clearance proposal. Feasibility Report (FR): Final approval from CCEA is under progress. Evacuation of coal by railways: A letter has been sent to PCOM/Eastern railway on 28.03.2024 about the proposed Godda to Nagarnabi alignment which confirmed that proposed rail line is within the PSCB block boundary. On 23.02.2024, Addl. Secretary, MoC sent DO letter to Chief Secretary, GoJ regarding PSCB GM/JJ land rate issue.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone