Towards compliance of FC Stage-I, The following payments done recently.
Rs. 38.07 Cr. deficit amount towards the cost of implementation of the CAT plan on 10.05.2025.
Rs. 38.07 Cr. deficit amount towards the cost of implementation of the CAT plan on 10.05.2025.
Rs. 8.98 Cr. towards the implementation of plantation activity within safety zone of PSOCP on 21.05.2025.
EDS compliance along with all fees, plans, schemes and studies (for obtaining FC Stage-II) in 09 sets submitted to DFO, Dumka on 22.05.2025. Currently proposal is with State Govt. Jharkhand under review since 20.06.2025.
Letter sent to M/s RITES on 20.06.2025 to expedite the construction work of Kurva Siding.
Meeting was held on 17.05.2025 between CEO/Railway Board and Secretary Power, it was decided to execute the Nagarnabi-Khatangi Railway Line project on deposit work basis. CEA was instructed to coordinate with WBPDCL, PSPCL and NUPPL for preparation of cost estimates and DPR segment wise at the earliest such that exercise may be completed within next two weeks time and DPR may be sent to Railways for execution of the project. | Forest Clearance:
* Reply of EDS compliance has been uploaded on 19.03.2024. Currently proposal is with PCCF (Nodal Officer), Ranchi.
* CMD/NLCIL vide letter dated 23rd March 2024 requested DG Forest and Spl Secretary, MoEF and CC for expediting the Forest clearance proposal.
Feasibility Report (FR): Final approval from CCEA is under progress.
Evacuation of coal by railways: A letter has been sent to PCOM/Eastern railway on 28.03.2024 about the proposed Godda to Nagarnabi alignment which confirmed that proposed rail line is within the PSCB block boundary.
On 23.02.2024, Addl. Secretary, MoC sent DO letter to Chief Secretary, GoJ regarding PSCB GM/JJ land rate issue. |